Asphalt-aggregate production

Assignee: Individual
•
Filing: 1976-08-26
•
Granted: 1980-01-08
•
Expires: 1996-08-26
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract In a process for producing asphalt-aggregate compositions in a conventional type dryer-mixer drum in which aggregate is exposed directly to flame and hot gases of combustion while it cascades in the rotating drum, and in which the flame and hot gases of combustion are directed into an input end of the drum, the improvement comprises separating the aggregate into a plurality of different portions or increments each having different particle size ranges, introducing the coarse or larger aggregate particles into the drum and directly exposing them to the flame, its radient heat, hot gases of combustion at the input end, and introducing the finer or smaller aggregate particles downstream from the input end and away from direct exposure to the flame and extremely hot gases in a temperature zone which will avoid overheating the fine particles. The improved apparatus includes means for introducing the coarse particles at the input drum end for direct exposure to the flame or hottest gases and means for introducing the fine or smaller particles in a cooler zone of the apparatus.

Inventors

  • 👤 Robert L. Mendenhall

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-10-28 10:03
CPC Classifications
F; F26; F26B; F26B11/00; F26B11/02; F26B11/026; C; C08; C08L; C08L95/00; C10; C10C; C10C3/00; C10C3/007; E; E01; E01C; E01C19/00; E01C19/02; E01C19/10; E01C19/1013; E01C19/1027; E01C19/1036; E01C19/1059; E01C19/1068; E01C19/1072; E01C2019/1081; E01C2019/1095

Claims Analysis

Total Claims: 13
Claim 1
Independent Claim 90 words
A process for producing asphalt-aggregate compositions comprising: (a) separating non-asphalt containing aggregate into coarse particles and fine particles; (b) introducing said coarse particles in a hot zone of a rotatable drum and gradually heating and advancing said particles toward an output drum end; (c) introducing said fine particles in said drum downstream from said hot zone in a cooler temperature zone; (d) gradually mixing and heating said coarse and fine particles; and (e) adding and mixing asphalt with said particles downstream from said hot zone to produce said asphalt-aggregate composition.
Claim 2
Dependent Claim 90 words
A process for producing asphalt-aggregate compositions comprising: (a) separating non-asphalt containing aggregate into coarse particles and fine particles; (b) introducing said coarse particles in a hot zone of a rotatable drum and gradually heating and advancing said particles toward an output drum end; (c) introducing said fine particles in said drum downstream from said hot zone in a cooler temperature zone; (d) gradually mixing and heating said coarse and fine particles; and (e) adding and mixing asphalt with said particles downstream from said hot zone to produce said asphalt-aggregate composition.
Claim 3
Dependent Claim 111 words
In a process for producing asphalt-aggregate composition by heating and mixing non-asphalt containing aggregate particles in a rotating drum into which hot gases of combustion are directed for said heating while gradually drawing said particles from an input drum end to an output end, and mixing asphalt with said particles to produce said composition, the improvement comprising separating said aggregate particles into a plurality of different particle sizes ranging from coarse to fine, introducing coarse particles at said drum input end, said coarse aggregate particles being exposed to said gases in a hot temperature zone, and introducing smaller sized aggregate particles in said drum in one or more cooler temperature zones.
Claim 4
Dependent Claim 111 words
In a process for producing asphalt-aggregate composition by heating and mixing non-asphalt containing aggregate particles in a rotating drum into which hot gases of combustion are directed for said heating while gradually drawing said particles from an input drum end to an output end, and mixing asphalt with said particles to produce said composition, the improvement comprising separating said aggregate particles into a plurality of different particle sizes ranging from coarse to fine, introducing coarse particles at said drum input end, said coarse aggregate particles being exposed to said gases in a hot temperature zone, and introducing smaller sized aggregate particles in said drum in one or more cooler temperature zones.
Claim 5
Dependent Claim 18 words
The process of claim 2 wherein the temperature in said hot zone is at least about 1000° F.
Claim 6
Dependent Claim 17 words
The process of claim 2 wherein the temperature in said cooler zones is below about 800° F.
Claim 7
Dependent Claim 17 words
The process of claim 3 wherein the temperature in said cooler zone is below about 800° F.
Claim 8
Dependent Claim 26 words
The process of claim 2 wherein said coarse particle size will be retained by a sieve having a mesh of between 4 and 10 U.S. series.
Claim 9
Dependent Claim 35 words
The process of claim 2 wherein said coarse particle size will be retained by a No. 8 U.S. series mesh and larger, and said fine sizes are about No. 10 U.S. series mesh and smaller.
Claim 10
Dependent Claim 47 words
The precess of claim 2 wherein said particles are separated into three size ranges comprising coarse particles retained by a No. 4 mesh sieve U.S. series, intermediate particles passing a No. 4 and retained by a No. 10 and fine particles passing greater than a No. 10.
Claim 11
Dependent Claim 16 words
The process of claim 2 wherein said asphalt is added immediately adjacent said cooler temperature zone.
Claim 12
Dependent Claim 72 words
A process for drying and heating non-asphalt containing aggregate comprising: (a) separating said aggregate into coarse particles and fine particles; (b) introducing said coarse particles in a hot zone of a rotatable drum and gradually advancing said particles toward an output drum end; (c) introducing said fine particles in said drum downstream from said hot zone in a cooler temperature zone; and (d) gradually mixing and heating said coarse and fine particles.
Claim 13
Dependent Claim 72 words
A process for drying and heating non-asphalt containing aggregate comprising: (a) separating said aggregate into coarse particles and fine particles; (b) introducing said coarse particles in a hot zone of a rotatable drum and gradually advancing said particles toward an output drum end; (c) introducing said fine particles in said drum downstream from said hot zone in a cooler temperature zone; and (d) gradually mixing and heating said coarse and fine particles.

References Cited (Backward Citations)

US1836261A Cited
US1954997A Cited
US3547411A Cited
US3614071A Cited
US3832201A Cited
US3971666A Cited
US3840215A Cited
US3866888A Cited
US3999743A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1983-01-07 1983-07-09 1984-01-08 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1987-01-07 1987-07-09 1988-01-08 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1991-01-07 1991-07-09 1992-01-08 $7700.00 Window Closed / Lapsed