Creation of multi-azimuth permeable hydraulic fractures
Assignee: Mobil Oil AS
•
Filing: 1987-12-29
•
Granted: 1989-05-30
•
Expires: 2007-12-29
Abstract
Abstract A process for creating multi-azimuth fractures by hydraulically fracturing a formation via a single wellbore where a special polymer is used as the fracturing fluid. An induced fracture is formed and a solidifiable gel material is injected into the fracture which is allowed to solidify. Thereafter, hydraulic fracturing with the special polymer is repeated causing the fracture trajectory to form contrary to the far-field in-situ stresses.
Inventors
- 👤 Duane C. Uhri
- 👤 Alfred R. Jennings, Jr.
Bibliographic Details
Application Number
—
Jurisdiction
US
Data Source
google_patents
Last Synchronized
2026-11-08 21:34
CPC Classifications
E; E21; E21B; E21B43/00; E21B43/25; E21B43/26; E21B43/261
Claims Analysis
Total Claims: 5
Claim 1
Independent Claim
136 words
A process for creating multi-azimuth fractures via hydraulic fracturing in a subterranean formation containing at least one wellbore comprising: (a) applying a hydraulic fracturing pressure into the formation through a liquid in said wellbore which pressure is sufficient to fracture said formation thereby forming at least one vertical fracture; (b) releasing said pressure and directing into said wellbore a solidifiable gel material sufficient to form a temporary plug within a desired time and distance within said formation; (c) allowing said solidifiable gel material to form a plug within said vertically created fracture; and (d) applying thereafter into said formation through a liquid in said wellbore a pressure sufficient to propagate at least one dendritic fracture from the existing vertical fracture because of the temporary plug in said fracture which dendritic fracture intersects a natural fracture system.
Claim 2
Dependent Claim
136 words
A process for creating multi-azimuth fractures via hydraulic fracturing in a subterranean formation containing at least one wellbore comprising: (a) applying a hydraulic fracturing pressure into the formation through a liquid in said wellbore which pressure is sufficient to fracture said formation thereby forming at least one vertical fracture; (b) releasing said pressure and directing into said wellbore a solidifiable gel material sufficient to form a temporary plug within a desired time and distance within said formation; (c) allowing said solidifiable gel material to form a plug within said vertically created fracture; and (d) applying thereafter into said formation through a liquid in said wellbore a pressure sufficient to propagate at least one dendritic fracture from the existing vertical fracture because of the temporary plug in said fracture which dendritic fracture intersects a natural fracture system.
Claim 3
Dependent Claim
29 words
The process as recited in claim 1 where in step (b) said plugging material comprises a solidifiable gel material which gel material breaks within about 0.5 to 24 hours.
Claim 4
Dependent Claim
23 words
The process as recited in claim 1 where steps (b), (c) and (d) are repeated until multi-azimuth fractures are created in said formation.
Claim 5
Dependent Claim
29 words
The process as recited in claim 1 where said formation contains a subterranean resource such as iron, copper ore, uranium ore, geothermal heat, coal, oil shale, or hydrocarbonaceous fluids.
References Cited (Backward Citations)
US3613789A
Cited
US3933205A
Cited
US4005753A
Cited
US4005750A
Cited
US4157116A
Cited
US4718490A
Cited
USPTO Annuity & Maintenance Windows
| Annuity Stage | Window Opens | Payment Deadline | Surcharge Period Until | Estimated Fee | Status |
|---|---|---|---|---|---|
| 3.5 Years (Year 4) | 1992-05-29 | 1992-11-28 | 1993-05-30 | $2000.00 | Window Closed / Lapsed |
| 7.5 Years (Year 8) | 1996-05-29 | 1996-11-28 | 1997-05-30 | $3760.00 | Window Closed / Lapsed |
| 11.5 Years (Year 12) | 2000-05-29 | 2000-11-28 | 2001-05-30 | $7700.00 | Window Closed / Lapsed |