Claim 1
Independent Claim
193 words
In a fluid flood process for enhancing the secondary recovery of hydrocarbons from a reservoir involving at least one pair of respective fluid injection and hydrocarbon recovery wells, having well bores, including the steps of (i) establishing a horizontal injection fracture for each injection well, said injection fracture extending substantially horizontally from said injection well bore proximate a lower portion of said reservoir and; (ii) establishing a horizontal recovery fracture for each recovery well, said recovery fracture extending substantially horizontally from said recovery well bore and the recovery fracture being vertically displaced from and above said injection fracture in the hydrocarbon reservoir, the improvement comprising the steps of: determining the azimuth of a vertical component of a fracture for said reservoir structure during the formulation of at least one of said fractures; disposing said injection wells and said recovery wells along lines substantially parallel to said azimuth of said vertical component; sizing the horizontal extent of said respective injection and recovery fractures to maximize overlap in the reservoir therebetween; and offsetting such injection and recovery wells to avoid a direct vertical path for the fluid flood between such respective injection and recovery fractures.
Claim 2
Dependent Claim
193 words
In a fluid flood process for enhancing the secondary recovery of hydrocarbons from a reservoir involving at least one pair of respective fluid injection and hydrocarbon recovery wells, having well bores, including the steps of (i) establishing a horizontal injection fracture for each injection well, said injection fracture extending substantially horizontally from said injection well bore proximate a lower portion of said reservoir and; (ii) establishing a horizontal recovery fracture for each recovery well, said recovery fracture extending substantially horizontally from said recovery well bore and the recovery fracture being vertically displaced from and above said injection fracture in the hydrocarbon reservoir, the improvement comprising the steps of: determining the azimuth of a vertical component of a fracture for said reservoir structure during the formulation of at least one of said fractures; disposing said injection wells and said recovery wells along lines substantially parallel to said azimuth of said vertical component; sizing the horizontal extent of said respective injection and recovery fractures to maximize overlap in the reservoir therebetween; and offsetting such injection and recovery wells to avoid a direct vertical path for the fluid flood between such respective injection and recovery fractures.
Claim 3
Dependent Claim
190 words
A process for enhancing the secondary recovery of hydrocarbons from a geological reservoir through at least one injection well bore and a plurality of production well bores which extend into the geological reservoir, the process comprising the steps of: injecting a fracture fluid through the at least one injection well bore into a lower portion of the geological reservoir thereby forming a substantially horizontal injection fracture having an upward vertical component, the vertical component being elongated in an azimuth direction; determining the azimuth of the elongation of the vertical component; disposing the production well bores in a line substantially parallel with the azimuth of the elongation of the vertical component and displaced from said at least one injection well bore; and injecting a fracture fluid through said production well bores thereby forming, from each production well bore, a substantially horizontal production fracture, extending out into overlapping relation with and displaced above said injection fracture, without intersecting said vertical component, so as to permit a vertical sweep of hydrocarbons, using a fluid flood through the geological reservoir between overlapping portions of the at least one injection fracture and the production fractures.
Claim 4
Dependent Claim
190 words
A process for enhancing the secondary recovery of hydrocarbons from a geological reservoir through at least one injection well bore and a plurality of production well bores which extend into the geological reservoir, the process comprising the steps of: injecting a fracture fluid through the at least one injection well bore into a lower portion of the geological reservoir thereby forming a substantially horizontal injection fracture having an upward vertical component, the vertical component being elongated in an azimuth direction; determining the azimuth of the elongation of the vertical component; disposing the production well bores in a line substantially parallel with the azimuth of the elongation of the vertical component and displaced from said at least one injection well bore; and injecting a fracture fluid through said production well bores thereby forming, from each production well bore, a substantially horizontal production fracture, extending out into overlapping relation with and displaced above said injection fracture, without intersecting said vertical component, so as to permit a vertical sweep of hydrocarbons, using a fluid flood through the geological reservoir between overlapping portions of the at least one injection fracture and the production fractures.
Claim 5
Dependent Claim
28 words
The process of claim 2, where in the steps of injecting comprises the step of propping at least one of the fractures with about number 12/20 mesh sand.
Claim 6
Dependent Claim
28 words
The process of claim 2 comprising the step of selecting, for the reservoir, a reservoir that is less than about 1200 feet below the surface of the earth.
Claim 7
Dependent Claim
38 words
The process of claim 2 wherein the step of injecting to form the at least one injection fracture comprises the step of forming a substantially disk shaped fracture having a radius of about 265 to about 285 feet.
Claim 8
Dependent Claim
36 words
The process of claim 2 or claim 5 wherein the steps of injecting to form the, production fractures comprise the step of forming substantially disk shaped fractures having a radius of about 235 to 250 feet.
Claim 9
Dependent Claim
18 words
The process of claim 2 comprising the step of spacing the wells at about 21/2 acre per well.
Claim 10
Dependent Claim
36 words
The process of claim 2 wherein the step of injection to form an injection fracture comprises the step of forming an injection fracture that has a larger horizontal area than each of the overlapping production fractures.
Claim 11
Dependent Claim
45 words
The process of claim 2 wherein the step of injecting to form the at least one injection fracture comprises the step of applying, in such at least one injection fracture, at least 60,000 to 70,000 gallons of fracture fluid to form a large horizontal fracture.
Claim 12
Dependent Claim
43 words
The process of claim 2 or 9 wherein the step of injecting to form the production fractures comprises the step of applying, in each of the production fractures, at least 35,000 to 38,000 gallons of fracture fluid to form a large horizontal fracture.
Claim 13
Dependent Claim
41 words
The process of claim 2 wherein the step of injecting to form the injection fractures comprises the step of forming the vertical component so that it extends vertically up to a horizontal plane intersecting the production an adjacent one of fractures.
Claim 14
Dependent Claim
60 words
The process of claim 2 wherein the step of injecting to form at least one injection well comprises the step of forming the horizontal injection fracture and vertical component having an opening between large opposite faces and wherein the size of the opening for the vertical component is less than the size of the opening for the horizontal injection fracture.
Claim 15
Dependent Claim
33 words
The process of claim 2 comprising the step of applying a vertical sweep of fluid through the injection well, the injection fracture and the reservoir to the production fracture and the production wells.
Claim 16
Dependent Claim
177 words
An enhanced secondary recovery of hydrocarbons system having a geological reservoir, at least one injection well bore and a plurality of production well bores which extend into the geological reservoir, comprising: in a lower portion of the geological reservoir, a substantially horizontal injection fracture extending from and in communication with said at least one injection well bore, said injection fracture having an upward vertical component, the vertical component being elongated in an azimuth direction; the production well bores each being positioned along a line substantially parallel with the azimuth of the elongation of the vertical component and displaced from said at least one injection well bore; and substantially horizontal production fractures, a different one of such production fractures in communication with and extending out from each of the production well bores into overlapping relation with and displaced above said injection fracture, without intersecting said vertical component, so as to permit a vertical sweep of hydrocarbons using a fluid flood, through the geological reservoir between overlapping portions of the at least one injection fracture and the production fractures.
Claim 17
Dependent Claim
177 words
An enhanced secondary recovery of hydrocarbons system having a geological reservoir, at least one injection well bore and a plurality of production well bores which extend into the geological reservoir, comprising: in a lower portion of the geological reservoir, a substantially horizontal injection fracture extending from and in communication with said at least one injection well bore, said injection fracture having an upward vertical component, the vertical component being elongated in an azimuth direction; the production well bores each being positioned along a line substantially parallel with the azimuth of the elongation of the vertical component and displaced from said at least one injection well bore; and substantially horizontal production fractures, a different one of such production fractures in communication with and extending out from each of the production well bores into overlapping relation with and displaced above said injection fracture, without intersecting said vertical component, so as to permit a vertical sweep of hydrocarbons using a fluid flood, through the geological reservoir between overlapping portions of the at least one injection fracture and the production fractures.
Claim 18
Dependent Claim
16 words
The system of claim 14 wherein the fractures are propped with about number 12/20 mesh sand.
Claim 19
Dependent Claim
20 words
The system of claim 14 wherein the reservoir is less than about 1200 feet below the surface of the earth.
Claim 20
Dependent Claim
28 words
The system of claim 14 wherein the at least one injection fracture comprises a substantially disk shaped fracture having a radius of about 265 to about 285 feet.
Claim 21
Dependent Claim
28 words
The system of claim 14 or claim 17 wherein the production fractures each comprises a substantially disk shaped fracture having a radius of about 235 to 250 feet.
Claim 22
Dependent Claim
17 words
The system of claim 14 wherein the spacing of the wells is about 21/2 acre per well.
Claim 23
Dependent Claim
21 words
The system of claim 15 wherein the injection fractures each have a larger horizontal area than each of the production fractures.
Claim 24
Dependent Claim
27 words
The system of claim 14 wherein the at least one injection fracture is large and, when formed, contained at least 60,000 to 70,000 gallons of fracture fluid.
Claim 25
Dependent Claim
32 words
The system of claim 14 or 21 wherein the production fractures are large and, before removal of pressure in the fracture fluid, contained at least 35,000 to 38,000 gallons of fracture fluid.
Claim 26
Dependent Claim
21 words
The system of claim 14 wherein vertical component extends up at least to a horizontal plane, intersecting the horizontal production fractures.
Claim 27
Dependent Claim
47 words
The system of claim 14 wherein each of the horizontal injection fractures and the vertical component have an opening between large opposite faces and wherein the size of the openings for the vertical component are less than the size of the opening for the horizontal injection fracture.
Claim 28
Dependent Claim
31 words
The system of claim 14 comprising a fluid passing through the injection well, the injection fracture and the reservoir to the production fractures and the well bores of the production wells.
Claim 29
Dependent Claim
22 words
The process of claim 1 comprising the step of propping at least some of the fractures with about number 12/20 mesh sand.
Claim 30
Dependent Claim
28 words
The process of claim 1 comprising the step of selecting, for the reservoir, a reservoir that is less than about 1200 feet below the surface of the earth.
Claim 31
Dependent Claim
30 words
The process of claim 1 comprising the step of forming, as each said injection fracture, a substantially disk shaped fracture having a radius of about 165 to about 285 feet.
Claim 32
Dependent Claim
31 words
The process of claim 1 or 28 comprising the step of forming, as each said recovery fracture, a substantially disk shaped fracture having a radius of about 235 to 250 feet.
Claim 33
Dependent Claim
18 words
The process of claim 1 comprising the step of spacing said wells at about 21/2 acre per well.
Claim 34
Dependent Claim
23 words
The process of claim 1 comprising the step of forming said injection fracture with a larger horizontal area than the overlapping recovery fracture.
Claim 35
Dependent Claim
29 words
The process of claim 1 forming at least one said injection fracture while applying at least 60,000 to 70,000 gallons of fracture fluid to form a large horizontal fracture.
Claim 36
Dependent Claim
35 words
The process of claim 1 or 32 comprising the step of forming at least one said recovery fracture while applying at least 35,000 to 38,000 gallons of fracture fluid to form a large horizontal fracture.
Claim 37
Dependent Claim
38 words
The process of claim 1 comprising the step of forming at least one said injection fracture with said vertical component so that the vertical component extends vertically up to a horizontal plane intersecting an adjacent said production fracture.
Claim 38
Dependent Claim
52 words
The process of claim 1 comprising the step of forming at least one said horizontal injection fracture with a vertical component having an opening between large opposite faces and wherein the size of the opening for the vertical component is less than the size of the opening for the horizontal injection fracture.
Claim 39
Dependent Claim
36 words
The process of claim 1 comprising the step of applying a vertical sweep of fluid through each said injection well, the injection fractures thereof and the reservoir to the recovery fractures and the recovery well bores.