Abstract A method of protecting a permeable formation penetrated by a well bore against damage by subsequent treatment operations. In protecting the formation against damage by cement used in installing a casing, a well bore is drilled through the formation and liquid composition capable of gelling is introduced into the area of the formation. After the gel is formed it is drilled out, leaving a sufficient amount still plugging the voids in the formation wall. Subsequently, after installing the casing, the gel reverts to liquid form, leaving the permeable formation in condition for production of the well. Preferably, the gel contains a breaker to cause the gel to revert to liquid form after a predetermined period of time.

Inventors

  • 👤 David O. Falk

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-09 08:03
CPC Classifications
E; E21; E21B; E21B7/00; C; C09; C09K; C09K8/00; C09K8/50; C09K8/504; C09K8/506; C09K8/508; C09K8/512; E21B33/00; E21B33/10; E21B33/13; E21B33/14

Claims Analysis

Total Claims: 22
Claim 1
Independent Claim 126 words
A method of protecting a permeable formation penetrated by a well bore against a subsequent treatment operation, comprising the steps of: providing support means in the well bore adjacent the lower boundary of the permeable formation to be protected; filling the bore between the support means and the uppermost point of the permeable formation to be protected with liquid composition capable of gelling; allowing the liquid composition to gel; drilling through the gel so as to open the well bore in the permeable formation, some of the gel remaining to plug the permeable formation in the well bore; carrying out the treatment operation; and causing the remaining gel to revert to a liquid, whereby the permeable formation is exposed after the treatment operation has been completed.
Claim 2
Independent Claim 126 words
A method of protecting a permeable formation penetrated by a well bore against a subsequent treatment operation, comprising the steps of: providing support means in the well bore adjacent the lower boundary of the permeable formation to be protected; filling the bore between the support means and the uppermost point of the permeable formation to be protected with liquid composition capable of gelling; allowing the liquid composition to gel; drilling through the gel so as to open the well bore in the permeable formation, some of the gel remaining to plug the permeable formation in the well bore; carrying out the treatment operation; and causing the remaining gel to revert to a liquid, whereby the permeable formation is exposed after the treatment operation has been completed.
Claim 3
Dependent Claim 22 words
A method according to claim 1, wherein the gel is caused to revert to a liquid by including a gel breaker therein.
Claim 4
Dependent Claim 21 words
A method according to claim 2, wherein the gel comprises a carboxylate-containing polymer crosslinked with a chromic carboxylate complex crosslinking agent.
Claim 5
Dependent Claim 13 words
A method according to claim 3, wherein the polymer is an acrylamide polymer.
Claim 6
Dependent Claim 32 words
A method according to claim 4, wherein the polymer is a polymer selected from the group consisting of polyacrylamide and partially hydrolyzed polyacrylamide, and the crosslinking agent is a chromic acetate complex.
Claim 7
Dependent Claim 20 words
A method according to claim 1, including the step of removing the support means after said drilling through the gel.
Claim 8
Dependent Claim 18 words
A method according to claim 6, wherein the support means is the temporary bottom of the well bore.
Claim 9
Independent Claim 108 words
A method of drilling a well bore through subsurface formations including a permeable formation, comprising the steps of: drilling a well bore through the permeable formation to at least the lower boundary thereof; filling the bore in the permeable formation with liquid composition capable of gelling, the liquid composition containing a gel breaker; allowing the gel to mature; drilling through the gel so as to open the well bore in the permeable formation, some of the gel remaining to plug the permeable formation in the well bore; installing a casing in the well bore in the permeable formation; and allowing the remaining gel to revert to a liquid.
Claim 10
Independent Claim 108 words
A method of drilling a well bore through subsurface formations including a permeable formation, comprising the steps of: drilling a well bore through the permeable formation to at least the lower boundary thereof; filling the bore in the permeable formation with liquid composition capable of gelling, the liquid composition containing a gel breaker; allowing the gel to mature; drilling through the gel so as to open the well bore in the permeable formation, some of the gel remaining to plug the permeable formation in the well bore; installing a casing in the well bore in the permeable formation; and allowing the remaining gel to revert to a liquid.
Claim 11
Dependent Claim 30 words
A method according to claim 8, including the step of cementing the casing to the well bore in the permeable formation prior to the remaining gel reverting to a liquid.
Claim 12
Dependent Claim 26 words
A method according to claim 9, including the step of perforating the casing in the permeable formation so as to permit production of the permeable zone.
Claim 13
Dependent Claim 21 words
A method according to claim 8, wherein the gel comprises a carboxylate-containing polymer crosslinked with a chromic carboxylate complex crosslinking agent.
Claim 14
Dependent Claim 33 words
A method according to claim 8 further comprising: providing support means in the well bore adjacent the lower boundary of the permeable formation prior to said filling the bore with said liquid composition.
Claim 15
Dependent Claim 26 words
A method according to claim 12 further comprising: removing said support means after the gel has been drilled through and prior to said installing the casing.
Claim 16
Independent Claim 201 words
A method of drilling a well bore through subsurface formations including upper and lower permeable formations, comprising the steps of: drilling a well bore through the upper permeable formation to at least the lower boundary thereof; filling the bore in the upper permeable formation with a first liquid composition capable of gelling, the first liquid composition containing a gel breaker; allowing the first liquid composition to gel; drilling through the gel so as to open the well bore in the upper permeable formation, some of the gel remaining to plug the permeable formation in the well bore; drilling a well bore through the lower permeable formation to at least the lower boundary thereof; filling the bore in the lower permeable formation with a second liquid composition capable of gelling, the second liquid composition containing a gel breaker; allowing the second liquid composition to gel; drilling through the second gel so as to open the well bore in the lower permeable formation, some of the gel remaining to plug the permeable formation in the well bore; installing a casing in the well bore in the first and second permeable formations; and allowing the remaining first and second gels to revert to liquids.
Claim 17
Independent Claim 201 words
A method of drilling a well bore through subsurface formations including upper and lower permeable formations, comprising the steps of: drilling a well bore through the upper permeable formation to at least the lower boundary thereof; filling the bore in the upper permeable formation with a first liquid composition capable of gelling, the first liquid composition containing a gel breaker; allowing the first liquid composition to gel; drilling through the gel so as to open the well bore in the upper permeable formation, some of the gel remaining to plug the permeable formation in the well bore; drilling a well bore through the lower permeable formation to at least the lower boundary thereof; filling the bore in the lower permeable formation with a second liquid composition capable of gelling, the second liquid composition containing a gel breaker; allowing the second liquid composition to gel; drilling through the second gel so as to open the well bore in the lower permeable formation, some of the gel remaining to plug the permeable formation in the well bore; installing a casing in the well bore in the first and second permeable formations; and allowing the remaining first and second gels to revert to liquids.
Claim 18
Dependent Claim 57 words
A method according to claim 14, including the steps of cementing the casing to the well bore in the first and second permeable formations prior to the remaining first and second gels reverting to liquids, and perforating the casing in at least one of the permeable formations so as to permit production of the associated permeable zone.
Claim 19
Dependent Claim 41 words
A method according to claim 14 further comprising: providing a support means in the well bore adjacent the lower boundary of the upper permeable formation prior to filling the well bore in the upper permeable formation with said first liquid composition.
Claim 20
Dependent Claim 31 words
A method according to claim 16 further comprising: removing said support means after the gel has been drilled through and prior to drilling said well bore through the lower permeable formation.
Claim 21
Dependent Claim 36 words
A method according to claim 14 further comprising: providing a support means in the well bore adjacent the lower boundary of the lower permeable formation prior to filling the well bore with said second liquid composition.
Claim 22
Dependent Claim 30 words
A method according to claim 18 further comprising: removing said support means after the gel has been drilled through and prior to installing a said casing in the well bore.

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1993-06-04 1993-12-04 1994-06-05 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1997-06-04 1997-12-04 1998-06-05 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2001-06-04 2001-12-04 2002-06-05 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag