Patent US4444263A successfully refreshed from Google Patents.
← Back to Patent Explorer
US4444263A Expired / Lapsed US ⏱️ 0.0 years remaining

Permanent thermal packer method

Assignee: Chevron USA Inc
•
Filing: 1983-04-22
•
Granted: 1984-04-24
•
Expires: 2003-04-22
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A permanent thermal packer is disclosed for sealing the annulus between an injection tubing string and a well casing. The packer is thermal cement and is placed from within the injection tubing string to seal a substantial portion of the annulus above the injection zone. The packer provides a means for sealing the annulus above the injection zone thus permitting insulating material to be placed in the annulus above the packer with the expectation that it will not be damaged by well bore fluids.

Inventors

  • 👤 Johan F. Ploeg
  • 👤 Arlo L. Oden

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-08 01:23
CPC Classifications
E; E21; E21B; E21B33/00; E21B33/10; E21B33/13; E21B33/134; E21B33/14; E21B33/16; E21B36/00; E21B36/003; Y; Y10; Y10S; Y10S166/00; Y10S166/901

Claims Analysis

Total Claims: 2
Claim 1
Independent Claim 289 words
A method for completing a hot fluid injection well along a cased outer conductor above a subsurface zone along said well into which said hot fluid is to be injected comprising the steps of: (a) assembling at the wellhead a string of injection tubing; (b) adding at least one upward facing, one-way packer to said injection tubing string; (c) adding a ported cement collar to said injection string above said upward facing, one-way packer; (d) running said assembled injection string into said cased outer conductor on the end of an inner well conductor; (e) positioning said ported cement collar at the desired position along said well above said subsurface zone; (f) flowing a liquid cement material down said inner well conductor, out said ported cement collar and into the annulus between said cased outer conductor and said inner well conductor and above said upward facing, one-way packer to fill said annulus along a substantial vertical length thereof; (g) allowing said cement to set to produce a cement packer capable of withstanding temperatures higher than the temperature of said hot fluids to be injected and to produce a complete seal of said annulus above said upward facing one-way packer and along said substantial vertical length of said annulus; (h) clearing the inside of said inner well conductor to provide access to said injection tubing and said subsurface zone along said inner conductor from said wellhead; (i) and filling at least a portion of the annulus between the outside of said inner well conductor and the inside of said outer well conductor and above said cement packer with an insulating material to reduce heat loss from said inner well conductor to the earth formations along said well above said cement packer.
Claim 2
Independent Claim 289 words
A method for completing a hot fluid injection well along a cased outer conductor above a subsurface zone along said well into which said hot fluid is to be injected comprising the steps of: (a) assembling at the wellhead a string of injection tubing; (b) adding at least one upward facing, one-way packer to said injection tubing string; (c) adding a ported cement collar to said injection string above said upward facing, one-way packer; (d) running said assembled injection string into said cased outer conductor on the end of an inner well conductor; (e) positioning said ported cement collar at the desired position along said well above said subsurface zone; (f) flowing a liquid cement material down said inner well conductor, out said ported cement collar and into the annulus between said cased outer conductor and said inner well conductor and above said upward facing, one-way packer to fill said annulus along a substantial vertical length thereof; (g) allowing said cement to set to produce a cement packer capable of withstanding temperatures higher than the temperature of said hot fluids to be injected and to produce a complete seal of said annulus above said upward facing one-way packer and along said substantial vertical length of said annulus; (h) clearing the inside of said inner well conductor to provide access to said injection tubing and said subsurface zone along said inner conductor from said wellhead; (i) and filling at least a portion of the annulus between the outside of said inner well conductor and the inside of said outer well conductor and above said cement packer with an insulating material to reduce heat loss from said inner well conductor to the earth formations along said well above said cement packer.

References Cited (Backward Citations)

US3131767A Cited
US3208521A Cited
US3561531A Cited
US3971441A Cited
US4333530A Cited
US4326586A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1987-04-24 1987-10-24 1988-04-24 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 1991-04-24 1991-10-24 1992-04-24 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 1995-04-24 1995-10-24 1996-04-24 $7700.00 Window Closed / Lapsed