Abstract

Abstract A method of gravel packing a well. A flow-reducing material is introduced into the annulus between a tubular liner and the well bore so as to collect at the perforations in the well bore and the apertures in the liner. This slows gravel slurry flow to the screen inner annulus and to the perforations to prevent gravel from bridging the annulus at these locations. The material is removed after the risk of bridging has passed. Various flow-reducing materials, such as wax flakes, salt, clay and gel, may be employed. The method is particularly useful in deviated wells.

Inventors

  • 👤 Donald E. Schroeder, Jr.

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-08 23:02
CPC Classifications
E; E21; E21B; E21B43/00; E21B43/02; E21B43/025; E21B43/04; E21B43/045

Claims Analysis

Total Claims: 30
Claim 1
Independent Claim 152 words
A method of gravel packing a well bore penetrating a subterranean formation, wherein the well bore contains perforations communicating with the formation throughout a portion of the length of the well bore, comprising: positioning a tubular liner within the perforated portion of the well bore, thereby defining an annulus between the liner and the well bore, the tubular liner containing a plurality of apertures throughout at least a substantial portion of the length thereof; introducing flow-reducing material into the annulus; introducing a slurry comprised of gravel suspended in fluid into the annulus; at least a portion of the flow-reducing material collecting at the well bore perforations and the liner apertures, slowing the flow of gravel into the perforations and apertures so as to prevent premature bridging of the gravel; and removing the flow-reducing material after the packing operation has proceeded to the point where there is little chance of premature bridging occurring.
Claim 2
Independent Claim 152 words
A method of gravel packing a well bore penetrating a subterranean formation, wherein the well bore contains perforations communicating with the formation throughout a portion of the length of the well bore, comprising: positioning a tubular liner within the perforated portion of the well bore, thereby defining an annulus between the liner and the well bore, the tubular liner containing a plurality of apertures throughout at least a substantial portion of the length thereof; introducing flow-reducing material into the annulus; introducing a slurry comprised of gravel suspended in fluid into the annulus; at least a portion of the flow-reducing material collecting at the well bore perforations and the liner apertures, slowing the flow of gravel into the perforations and apertures so as to prevent premature bridging of the gravel; and removing the flow-reducing material after the packing operation has proceeded to the point where there is little chance of premature bridging occurring.
Claim 3
Dependent Claim 16 words
The method of claim 1, wherein the well bore extends at an angle to the vertical.
Claim 4
Dependent Claim 21 words
The method of claim 2, wherein the flow-reducing material collects substantially sequentially from the upstream to the downstream perforations and apertures.
Claim 5
Dependent Claim 33 words
The method of claim 3, wherein the flow-reducing material is introduced into the annulus in an aqueous medium and wherein the material has a specific gravity less than the specific gravity of water.
Claim 6
Dependent Claim 18 words
The method of claim 1, wherein the flow-reducing material is introduced into the annulus in an aqueous medium.
Claim 7
Dependent Claim 30 words
The method of claim 1, wherein the flow-reducing material is introduced into the annulus by intermingling the material with an initial portion of the gravel slurry introduced into the annulus.
Claim 8
Dependent Claim 22 words
The method of claim 6, wherein the flow-reducing material is introduced with the first 10%-20%, by volume, of the introduced gravel slurry.
Claim 9
Dependent Claim 29 words
The method of claim 1, wherein the flow-reducing material is introduced into the annulus after an initial portion of the gravel slurry has been placed in the well bore.
Claim 10
Dependent Claim 21 words
The method of claim 1, wherein the flow-reducing material comprises particles which melt when subjected to heat above their melting point.
Claim 11
Dependent Claim 11 words
The method of claim 9, wherein the particles comprise wax flakes.
Claim 12
Dependent Claim 18 words
The method of claim 1, wherein the flow-reducing material comprises salt particles introduced in a saturated aqueous medium.
Claim 13
Dependent Claim 17 words
The method of claim 11, wherein the salt particles are removed by contacting them with unsaturated water.
Claim 14
Dependent Claim 17 words
The method of claim 1, wherein the flow-reducing material is benzoic acid introduced in an aqueous medium.
Claim 15
Dependent Claim 16 words
The method of claim 1, wherein the flow-reducing material comprises clay introduced in an aqueous medium.
Claim 16
Dependent Claim 16 words
The method of claim 14, wherein the clay is removed by contacting it with mud acid.
Claim 17
Dependent Claim 13 words
The method of claim 1, wherein the flow-reducing material comprises a viscous gel.
Claim 18
Dependent Claim 17 words
The method of claim 16, wherein the gel is removed by contacting it with a gel breaker.
Claim 19
Dependent Claim 12 words
The method of claim 1, wherein the well bore includes a casing.
Claim 20
Dependent Claim 17 words
The method of claim 1, wherein the liner includes a screen extending around the outer circumference thereof.
Claim 21
Dependent Claim 39 words
The method of claim 1, wherein a wash pipe is positioned within the liner, whereby fluid from the slurry flows through lower apertures in the liner and up the wash pipe to the surface during a gravel packing operation.
Claim 22
Dependent Claim 194 words
In a method of gravel packing a well bore penetrating a subterranean formation, wherein the well bore contains perforations communicating with the formation throughout a portion of the length of the well bore, and wherein a tubular liner is positioned within the perforated portion of the well bore, thereby defining an annulus between the liner and the well bore, the tubular liner containing a plurality of apertures throughout at least a substantial portion of the length thereof, and wherein a slurry of gravel suspended in fluid is introduced into the annulus, whereby the gravel is deposited and packed in the annulus and the slurry fluid is caused to flow through at least downstream apertures in the liner, the improvement comprising: introducing flow-reducing material into the annulus prior to introducing substantial portions of the gravel slurry; at least a portion of the flow-reducing material collecting at upstream well bore perforations and liner apertures, slowing the flow of gravel into the perforations and apertures so as to prevent premature bridging of the gravel; and removing the flow-reducing material after the packing operation has proceeded to the point where there is little chance of premature bridging occurring.
Claim 23
Dependent Claim 194 words
In a method of gravel packing a well bore penetrating a subterranean formation, wherein the well bore contains perforations communicating with the formation throughout a portion of the length of the well bore, and wherein a tubular liner is positioned within the perforated portion of the well bore, thereby defining an annulus between the liner and the well bore, the tubular liner containing a plurality of apertures throughout at least a substantial portion of the length thereof, and wherein a slurry of gravel suspended in fluid is introduced into the annulus, whereby the gravel is deposited and packed in the annulus and the slurry fluid is caused to flow through at least downstream apertures in the liner, the improvement comprising: introducing flow-reducing material into the annulus prior to introducing substantial portions of the gravel slurry; at least a portion of the flow-reducing material collecting at upstream well bore perforations and liner apertures, slowing the flow of gravel into the perforations and apertures so as to prevent premature bridging of the gravel; and removing the flow-reducing material after the packing operation has proceeded to the point where there is little chance of premature bridging occurring.
Claim 24
Dependent Claim 33 words
The method of claim 21, wherein the well bore extends at an angle to the vertical and wherein the flow-reducing material collects substantially sequentially from the upper to the lower perforations and apertures.
Claim 25
Dependent Claim 30 words
The method of claim 21, wherein the flow-reducing material has a specific gravity less than the specific gravity of water and is introduced into the annulus in an aqueous medium.
Claim 26
Dependent Claim 30 words
The method of claim 21, wherein the flow-reducing material is introduced into the annulus by intermingling the material with an initial portion of the gravel slurry introduced into the annulus.
Claim 27
Dependent Claim 21 words
The method of claim 21, wherein the flow-reducing material comprises particles which melt when subjected to heat above their melting point.
Claim 28
Dependent Claim 26 words
The method of claim 21, wherein the flow-reducing material comprises salt particles introduced in a saturated aqueous medium and removed by contacting them with unsaturated water.
Claim 29
Dependent Claim 24 words
The method of claim 21, wherein the flow-reducing material comprises clay introduced in an aqueous medium and removed by contacting it with mud acid.
Claim 30
Dependent Claim 23 words
The method of claim 21, wherein the flow-reducing material comprises a viscous gel which is removed by contacting it with a gel breaker.

References Cited (Backward Citations)

US3273641A Cited
US3216497A Cited
US3826310A Cited
US3880233A Cited
US4018282A Cited
US4703799A Cited
US5062484A Cited
US5165476A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 1996-12-13 1997-06-14 1997-12-14 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2000-12-13 2001-06-14 2001-12-14 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2004-12-13 2005-06-14 2005-12-14 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags