Patent US5755286A successfully refreshed from Google Patents.
← Back to Patent Explorer
US5755286A Expired / Lapsed US ⏱️ 0.0 years remaining

Method of completing and hydraulic fracturing of a well

Assignee: Ely and Associates Inc
•
Filing: 1997-05-27
•
Granted: 1998-05-26
•
Expires: 2017-05-27
📄 Original PDF 🌐 Google Patents 🔄 Sync Now

Abstract

Abstract A method for completing and increasing the production rate from a cased well which may produce solids through perforations during production is provided. A gravel pack screen is placed in the well along with equipment in the tubing string to control flow from inside to outside the tubing below a production packer. The rig used to place the equipment may then be released from the well. The well is then hydraulically fractured. If the well is producing from a high permeability zone, the hydraulic fracture is preferably formed with the tip screen-out technique. The method can also be used in a well already containing production tubing without moving a rig on the well to remove the tubing from the well and can be used in a well not yet perforated by adding tubing-conveyed perforating apparatus below the screen.

Inventors

  • 👤 Charles D. Ebinger

Bibliographic Details

Application Number —
Jurisdiction US
Data Source google_patents
Last Synchronized 2026-11-08 22:16
CPC Classifications
E; E21; E21B; E21B43/00; E21B43/25; E21B43/26; E21B43/02; E21B43/04; E21B43/10

Claims Analysis

Total Claims: 5
Claim 1
Independent Claim 170 words
A method for completing a well and hydraulically fracturing a productive zone penetrated by the well, the well having casing and tubing, the casing having perforations into the productive zone, comprising the steps of: (a) placing in the casing through the tubing a screen assembly, the screen assembly comprising a gravel pack screen, the gravel pack screen having a lower end and an upper end and being placed below the tubing and opposite the perforations in the casing, the gravel pack screen being closed on the lower end and connected to a blank pipe on the upper end, the blank pipe being connected to a vent screen, the vent screen having a lower end and an upper end, the blank pipe being connected to the lower end, the upper end of the vent screen being closed; (b) hydraulically fracturing the well by pumping fluid and proppant down the tubing string and around the screen assembly; and (c) washing proppant from the tubing and casing down to below the vent screen.
Claim 2
Independent Claim 170 words
A method for completing a well and hydraulically fracturing a productive zone penetrated by the well, the well having casing and tubing, the casing having perforations into the productive zone, comprising the steps of: (a) placing in the casing through the tubing a screen assembly, the screen assembly comprising a gravel pack screen, the gravel pack screen having a lower end and an upper end and being placed below the tubing and opposite the perforations in the casing, the gravel pack screen being closed on the lower end and connected to a blank pipe on the upper end, the blank pipe being connected to a vent screen, the vent screen having a lower end and an upper end, the blank pipe being connected to the lower end, the upper end of the vent screen being closed; (b) hydraulically fracturing the well by pumping fluid and proppant down the tubing string and around the screen assembly; and (c) washing proppant from the tubing and casing down to below the vent screen.
Claim 3
Dependent Claim 13 words
The method of claim 1 wherein the screen assembly further comprises a centralizer.
Claim 4
Dependent Claim 12 words
The method of claim 2 wherein the centralizer is a bow centralizer.
Claim 5
Dependent Claim 16 words
The method of claim 1 wherein the blank pipe is at least 30 feet in length.

References Cited (Backward Citations)

US2753940A Cited
US4253522A Cited
US4372384A Cited
US4685519A Cited
US4969524A Cited
US5062484A Cited
US5174379A Cited
US5332038A Cited
US5443117A Cited
US5417284A Cited
US5598891A Cited
US5435391A Cited
US5597040A Cited

USPTO Annuity & Maintenance Windows

Annuity Stage Window Opens Payment Deadline Surcharge Period Until Estimated Fee Status
3.5 Years (Year 4) 2001-05-25 2001-11-24 2002-05-26 $2000.00 Window Closed / Lapsed
7.5 Years (Year 8) 2005-05-25 2005-11-24 2006-05-26 $3760.00 Window Closed / Lapsed
11.5 Years (Year 12) 2009-05-25 2009-11-24 2010-05-26 $7700.00 Window Closed / Lapsed

Assigned Categories & Tags

No categories assigned to this patent yet.

Assign Category Tag